When last we looked at the end of March, the house had just been enclosed and the heating, rough plumbing and rough electrical had just been installed. We now have the insulation and drywall installed and the entire interior painted. The oak flooring is installed and the cabinets are being installed. The main remaining items are the tile floors, interior doors and trim, appliance installation, and the finish plumbing and electrical work. When we first began this adventure over a year ago, we were hoping to move in by Christmas. When we had the first contractor walk out on us, we adjusted the goal to Easter. Anybody for the 4th of July? We think it should be virtually finished by then, but we plan on spending the rest of July moving our stuff from the rental house. The following summarizes the steps that occurred in April and May.
Once 
  the house was enclosed, the next step was to insulate it. This is a view of 
  one living room corner after the insulation was installed. 
Next 
  came the drywall - being delivered on the left and after it was installed in 
  the living/dining room on the right.
Then 
  came the paint. While it looks like this might be a biohazard response crew, 
  we were assured that they were painters. The guy on the left is mixing the paint. 
  It is then pumped from the truck to the spray gun as seen on the right. After 
  it is sprayed on, it is smoothed out with a roller. That's what the guy in front 
  of the window is doing.
Once 
  the walls and ceilings were painted, we could install the oak flooring in the 
  living, dining room, and bedrooms. What you see is the nailing which, it turns 
  out, is the easy part. The hard part is laying out the oak boards to get them 
  aligned and staggered properly for both visual and strength reasons.
The 
  concrete boards have been installed in the kitchen and bath rooms in preparation 
  for the floor tile. At the same time, the kitchen cabinets are being installed. 
  They were delivered in the middle of April and were stacked in the garage awaiting 
  their turn, which has finally come. The tall cabinet in the corner will house 
  the ovens. The peninsula in front separates the kitchen from the dining nook.
Mean 
  while, on the outside, we had the concrete slabs for the main basement door, 
  the side garage door, and front porch poured. On the left, they're doing the 
  front porch. We wanted a rough pebblely finish. It turns out this is achieved 
  by ordering a particular concrete mix, pouring it and smoothing it as usual, 
  but then flushing the surface off with a hose after it is partially dry.
 For 
  the last update, the decks were just being installed. Ralph, our contractor, 
  finished the deck floors. However, since I was bugging him for a job beyond 
  priming the outdoor trim, he suggested I do the deck rails. The first plan was 
  to go with stainless steel which would have meant simply buying the metal posts 
  and installing them. That turned out to be too expensive and Ralph suggested 
  framing galvanized iron mesh in a cedar frame. This turned out to be a much 
  harder job. In addition to building the frame, it required grooves to be cut 
  in the frame to accept the iron mesh. The hardest part, though, was laying out 
  the posts. For maximum strength, every span between posts had to be a multiple 
  of 4 inches since that was the size of the mesh, but the total length (alas) 
  was never quite a multiple of 4 inches. We do like the finished product (shown 
  here). Or should I say almost finished. As I was cutting the last groove in 
  a 16 foot 2x4, my radial arm saw of 15 years died after 8 feet. I'm planning 
  on buying a new one on Saturday so I can finish the job.
For 
  the last update, the decks were just being installed. Ralph, our contractor, 
  finished the deck floors. However, since I was bugging him for a job beyond 
  priming the outdoor trim, he suggested I do the deck rails. The first plan was 
  to go with stainless steel which would have meant simply buying the metal posts 
  and installing them. That turned out to be too expensive and Ralph suggested 
  framing galvanized iron mesh in a cedar frame. This turned out to be a much 
  harder job. In addition to building the frame, it required grooves to be cut 
  in the frame to accept the iron mesh. The hardest part, though, was laying out 
  the posts. For maximum strength, every span between posts had to be a multiple 
  of 4 inches since that was the size of the mesh, but the total length (alas) 
  was never quite a multiple of 4 inches. We do like the finished product (shown 
  here). Or should I say almost finished. As I was cutting the last groove in 
  a 16 foot 2x4, my radial arm saw of 15 years died after 8 feet. I'm planning 
  on buying a new one on Saturday so I can finish the job.
As 
  part of the final grading of the lot, we had them redo our short private road 
  shared by four lots. On the left is the Apple Tree Lane street sign which was 
  originally installed in 1994, but was somehow torn out and lost. We discovered 
  it under eight years of brush growth and I reinstalled it at the "intersection" 
  with Scenic Avenue. On the right is a picture of Apple Tree Lane now appropriately 
  crowned to handle the famous Seattle rains.
On 
  the left is the front door and porch and, on the right, the garage doors. The 
  paint patches next to the front door was done by Sooja to test colors.