The 
  lot slopes downhill from west to east. This is a view from the cul-de-sac at 
  the southeast corner of the lot looking up the hill. This is actually a picture 
  from 1995. The trees are much bigger now and there are a lot more of them as 
  well as miscellaneous brush. The douglas fir on the right side of the picture 
  is the only real tree we had to sacrifice. It's in the middle of the living 
  room.
The 
  house site was excavated by 9/14. The basement extends only under the main part 
  of the house, i.e. below the living room, dining room, bedrooms, and baths. 
  In the photo, the lowest level is the excavation for the basement. Where the 
  dirt rises on the left is the crawl space under the kitchen and laundry room. 
  The slight rise above that is to the garage floor.
By 
  9/19, the forms needed to pour the concrete footings were set. The photo shows 
  the footing layout along the wall between the house and the garage. The garage 
  is to the left and extends to the center of the photo in the foreground. The 
  section behind that garage extension is under what will become the laundry room.
The 
  concrete footings were poured on 9/20. As they were poured, the vertical reenforcement 
  bars were installed as shown in this photo. Once dried, the footing forms were 
  removed and the crew began installing the forms needed to pour the concrete 
  walls. The s-shaped footing is the one made from the forms in the middle of 
  the photo above, i.e. the wall between the house and garage, but from a different 
  angle.
The 
  walls were poured on 9/26. That meant getting concrete trucks and a concrete 
  pumping machine up the tiny road to our lot and guiding the pumped concrete 
  through the hose into the forms.
The 
  forms were removed from the walls on 9/30. The walls were smoothed and and then 
  waterproofed as shown in the photo. Insulation styroform two inches thick was 
  installed over the waterproofing. Ralph then laid out a drainage system around 
  the foundation designed to take away any standing water that could eventually 
  seep into the basement. Then the hole shown was backfilled with sand. The sand 
  is used to allow any water to easily penetrate to the drainage system and be 
  carried away from the house.
Once 
  all the concrete walls were backfilled, attention turned to the slabs for the 
  basement and garage. The first step was to put in 8 inches of sand and tamp 
  it solidly down. That's already been done in the photo. Next the sand is prepared 
  for the interior support wall footings. Instead of setting forms, this is done 
  by digging trenches in the sand at the appropriate places. When the slab is 
  poured, the trenches will be filled in providing a one foot footing (concrete 
  in the eight inches of trench plus the 4 inch slab). The photo shows the trenches 
  being dug.
In addition to the trenches for the footings, all the gravity drain pipes, i.e. sewer lines, need to be installed before the slab is poured. The two pipes to the left in the middle set are for the basement bath (one is the drain, the other a vent). The ones to the right of those will be extended upward to handle the bathrooms on the main floor. Finally, the diagonal pipe going off to the left just beyond the front footing is for the kitchen drain.
Next 
  a plastic vapor barrier is layed down as shown on the left. The iron bars are 
  to reenforce the footings. The iron grid is used to reenforce the slabs. Finally 
  the slab was poured along with the concrete stairs to the workshop (see photo 
  on right).
The next step will be the framing to begin about mid-November when the framing crew becomes available. In the mean time, work is proceeding on the septic system. As noted in the background material, we originally committed to a sand filter system since we didn't own the area that perked well enough for a traditional septic system. By the time we found Ralph, we had closed the deal on the additional 100 feet which would be enough for a septic system. On 9/14, perk holes were dug and a couple were found to be reasonably good. An engineer concurred on 9/18 and the county approved the location on 9/20. A new design was drawn up by the engineer and a new permit was submitted to the county on 9/25. It has recently been approved and clearing the area for the new septic design began the week of 10/21.
That brings us up to date which is in fact October 24, 2002.