When last we looked at the end of January, the framing of the house had just been completed and tar paper was being applied to the roof. We now have the outside mostly done as well as the heating, rough plumbing, and rough electrical. The framing inspection was completed this week and we're clear to start closing up the inside. Insulation is scheduled to be put in this week and the drywalling starts next week. The following summarizes the steps that occurred in February and March.
 First 
  the entire roof was covered with tar paper and the entire house was wrapped 
  in the obligatory Tyvek. The angle here is the main entry/porch.
First 
  the entire roof was covered with tar paper and the entire house was wrapped 
  in the obligatory Tyvek. The angle here is the main entry/porch.
 Next 
  comes the siding with installation starting at the end of the garage. It started 
  there because the windows need to be installed before the siding (it buts up 
  against them) and the windows were not yet installed. But the end of the garage 
  doesn't have any windows. We selected an artificial material called Hardiplank 
  whose consistency is more like concrete, but is designed to look like wood. 
  The reason - lower maintenance (that's an ongoing theme).
Next 
  comes the siding with installation starting at the end of the garage. It started 
  there because the windows need to be installed before the siding (it buts up 
  against them) and the windows were not yet installed. But the end of the garage 
  doesn't have any windows. We selected an artificial material called Hardiplank 
  whose consistency is more like concrete, but is designed to look like wood. 
  The reason - lower maintenance (that's an ongoing theme).
 At 
  the same time, the Hardiplank was covering Tyvek, Pabco shingles were covering 
  the tar paper on the roof. Yes that is a hole in the roof - one of three skylights. 
  Another can be seen covered with plywood. The third is out of the picture to 
  the left.
At 
  the same time, the Hardiplank was covering Tyvek, Pabco shingles were covering 
  the tar paper on the roof. Yes that is a hole in the roof - one of three skylights. 
  Another can be seen covered with plywood. The third is out of the picture to 
  the left.
 Eventually 
  the entry side looked like this with the windows, siding, and shingles in place. 
  You can also see the skylights and the first of many pipes poked through the 
  roof. In this case a plumbing vent and a "whole house exhaust fan" 
  (required by code) in the laundry room.
Eventually 
  the entry side looked like this with the windows, siding, and shingles in place. 
  You can also see the skylights and the first of many pipes poked through the 
  roof. In this case a plumbing vent and a "whole house exhaust fan" 
  (required by code) in the laundry room.
 The 
  view side now looks like this with the windows and doors installed and most 
  of the siding on. The siding work will take about one day to complete and I 
  was waiting for it to be completed before doing this update. Then I discovered 
  that part of the remaining effort is to cover the overhang above the basement 
  door and that has to be insulated before being covered. So the siding guy has 
  been on hold. I decided to update without the siding complete.You can see a 
  couple more pipes: the furnance exhaust to the left and the propane fireplace 
  exhaust to the right. There is a third pipe off to the left that serves as an 
  air intake for the furnance. Separately, the gutters have been installed. We 
  went with the Leafguard gutters (the covered ones that are guaranteed to keep 
  the leaves out) for (you guessed it) low maintenance.
The 
  view side now looks like this with the windows and doors installed and most 
  of the siding on. The siding work will take about one day to complete and I 
  was waiting for it to be completed before doing this update. Then I discovered 
  that part of the remaining effort is to cover the overhang above the basement 
  door and that has to be insulated before being covered. So the siding guy has 
  been on hold. I decided to update without the siding complete.You can see a 
  couple more pipes: the furnance exhaust to the left and the propane fireplace 
  exhaust to the right. There is a third pipe off to the left that serves as an 
  air intake for the furnance. Separately, the gutters have been installed. We 
  went with the Leafguard gutters (the covered ones that are guaranteed to keep 
  the leaves out) for (you guessed it) low maintenance.

 You 
  also see the beams bolted to the house for the two decks above. At left, the 
  concrete footings for the support posts have been poured and on the right the 
  framing of one deck has been started.
You 
  also see the beams bolted to the house for the two decks above. At left, the 
  concrete footings for the support posts have been poured and on the right the 
  framing of one deck has been started. 
And 
  now for the inside. First we had to bring the water, electricity, and telephone 
  lines from the temp site along side the driveway up to the house. The trench 
  that accomplished that is being refilled here. At the same time, the LP gas 
  tank was installed and a trench on the other side of the house ran the LP line 
  to the house.
The 
  plumbing has been roughed in. This is the back side of the laundry room including 
  the vent pipe going up and out the roof that we saw before. The right pipes 
  go to the washer and the left ones to the laundry sink. The little copper pipe 
  in the lower left corner (that you probably can't make out) is another consequence 
  of the local code. Since we once incurred a lot of damage in our old house when 
  a washer hose burst while we were gone. I had them install a drain in the floor 
  just in case. Since there's a drain, there's a trap in it to shield us from 
  sewer gases just like in the sinks. However, since this one is unlikely to be 
  used, it could dry up and expose us to sewer gases. Hence, the code calls for 
  a special water pipe and valve that will automatically keep the trap full of 
  water. Thank heaven Island County is protecting me.
 The 
  heating ducts and furnace were installed. The ducts (in this case the main cold 
  air return) are much bigger than I've seen before presumably to maximize flow. 
  Since the ducts here will be above the insulation in the ceiling of the living 
  room, they needed to be insulated separately. Since the furnance was installed, 
  it's been running continuously to dry out the house from all the rain water 
  the wood absorbed before the roof was on. We went through over 300 gallons of 
  LP in a couple of weeks. I'll be glad to get that insulation in. But it has 
  served its purpose. The water content has come down 4 to 6% and is approaching 
  the goal of 10%. Hence the go ahead for insulating this week.
The 
  heating ducts and furnace were installed. The ducts (in this case the main cold 
  air return) are much bigger than I've seen before presumably to maximize flow. 
  Since the ducts here will be above the insulation in the ceiling of the living 
  room, they needed to be insulated separately. Since the furnance was installed, 
  it's been running continuously to dry out the house from all the rain water 
  the wood absorbed before the roof was on. We went through over 300 gallons of 
  LP in a couple of weeks. I'll be glad to get that insulation in. But it has 
  served its purpose. The water content has come down 4 to 6% and is approaching 
  the goal of 10%. Hence the go ahead for insulating this week.
The 
  electrical has been roughed in. The electrician ran lots of separate circuits. 
  Hence the big breaker box at left. While he was doing that, I ran the low voltage 
  wiring for TV signals (black coax), telephone (white), and speakers (blue) to 
  a future patch panel in the basement. I decided not to run cat5 for a computer 
  network opting instead to use wireless technology when we install a home networking 
  arrangement. I also ran a couple of empty conduits for unforseen future needs.

 And 
  finally, while we continue to build the house, Sooja has been buying from conservation 
  districts and gathering from friends all sorts of plants and trees. They're 
  being temporarily planted in the back area over the septic system where the 
  final grading has been done. There are also potted plants that we've put in 
  a small fence enclosure to protect our investment from the deer. To date, the 
  only permanent planting is some ground cover over the septic field itself. This 
  is just the initial landscaping phase. We estimate it should be all done in 
  about 10 years.
And 
  finally, while we continue to build the house, Sooja has been buying from conservation 
  districts and gathering from friends all sorts of plants and trees. They're 
  being temporarily planted in the back area over the septic system where the 
  final grading has been done. There are also potted plants that we've put in 
  a small fence enclosure to protect our investment from the deer. To date, the 
  only permanent planting is some ground cover over the septic field itself. This 
  is just the initial landscaping phase. We estimate it should be all done in 
  about 10 years.